Procurement Example: P3

Long Beach Civic Center 

The Civic Center Project involves 14.89 acres in downtown Long Beach that is currently utilized for the existing City Hall, Main Library, former State Courthouse, a destination park and related parking.

Background

The City commissioned an architectural firm to carry out detailed planning and engage with stakeholders, aiming to transform the Civic Center through the "Re-envisioning the Civic Center" initiative:

  • The project's goal is to transform the Civic Center into a dynamic area blending public and private spaces, including a prominent Civic Plaza. Objectives include:

  • Enhancing connectivity between the new Civic Center and Downtown.

  • Turning Lincoln Park into a sought-after park with amenities for visitors, residents, and Downtown employees.

  • Lowering maintenance costs, improving energy efficiency, consolidating offsite leases, and achieving cost neutrality.

  • Exploring private development opportunities and/or selling surplus property for private development.

Evaluating Alternatives

Three alternatives were considered:

  • Retrofit Alternative

  • Relocation Alternative

  • Re-Build Alternative

The Retrofit and Relocation Alternatives were determined to be infeasible. The Re-Build Alternative under a P3/ DBFOM (Design, Build, Finance, Operate & Manage) delivery model was determined to offer the best value and lowest risk to the City.

Risk Transfer

Value for Money

Benefits

  • Fastest path to new, seismically superior facilities

  • City transfers to the Project Team design and construction risk, including entitlements, change orders, cost overruns and construction delays

  • Lower maintenance and operation costs at the same performance level over life of the facility, resulting in lower cost

  • City does not pay Project Team until City occupies the new facilities. At that time, the City will be obligated to make lease payments for 40 years

  • At the end of the 40 year lease, the facility is transferred to the City at no cost at a Facility Condition Index of 15% or less, indicating the building is in Good or better condition

Project Goals

  • Ensure the City's lease payments for the new City Hall and Main Library, including operations and maintenance, approximate current costs, but include annual CPI increases

  • Shift risks associated with design, development, entitlement, financing, construction, operations and maintenance to the Project Team

  • Incorporate a 40-year life-cycle Operations and Maintenance contract for the Civic Center as part of the City's current costs

  • Require ownership of the facilities to revert at no cost to the City at the end of the contract at a "good" or better condition.

Process

DBFOM (Design, Build, Finance, Operate & Manage) Process

  • Issue a Request for Qualifications (RFQ) for DBFOM in April 2013.

  • Issue an RFQ for a P3 Consultant in September 2013.

  • Announce a shortlist of RFQ respondents on October 22, 2013.

  • Collaborate with the P3 Consultant to prepare and issue a Request for Proposals (RFP) on February 28, 2014, along with an evaluation matrix to score the proposals.

  • Review, evaluate, and score the RFP responses.

  • Recommend a preferred Project Team to the City Council.

  • Enter into an Exclusive Negotiating Agreement (ENA) with the Project Team to exclusively negotiate the general technical and financial terms of the Project, including risk allocation.

  • Develop a Term Sheet that details those terms and risk allocations in a formal agreement, guiding the project through the entitlement period.

  • Formulate a Global Executory Agreement to oversee the negotiation process and the obligations of the parties in preparing and executing agreements for the lease/leaseback, conveyance of development rights for private development, and achieving commercial and financial closure.

Timeline


Team Members

Owner’s Consultants

  • P3 Consultant

  • Architectural services

  • Assist in the development of the Request for Proposal

  • Assist in RFP Evaluation, due diligence and selection

  • Project Management including a workplan and schedule to ensure identification, coordination, tracking and completion of necessary tasks

  • Advisory Services including financial, commercial, and technical support to help the City manage risk, lead negotiations, and prepare the needed documents to reach commercial and financial close

  • Community Outreach Support including maintenance of the City's website, tracking of comments and surveys, monitoring and analyzing site traffic and participating in public and community meetings

P3 Consultant’s Team

  • Architectural firm

  • Various engineering disciplines

  • Cost consultant

  • Community outreach consultant

  • Legal representation

  • Economic consultant

Legal Advisor

  • Negotiation, preparation, revision and finalization of the legal documents necessary to achieve commercial and financial close:

  • Exclusive Negotiation Agreement

  • Term Sheet

  • Memorandum of Understanding

  • Global Executory Agreement

  • Closing Documents:

  • Concession Agreement

  • Ground Lease

  • Space Leases

  • Development Agreement for Private Development

  • Creation of one or more special purpose non-profit entity for the purpose of issuing bonds

  • Bond counsel

Financial Advisor

  • Perform as peer reviewer and attend all meetings through financial close

  • Assessing factors that may impact City finances, budget or risk

  • Provide advice and support with regard to development of the final financial plan, the financing entities and debt structuring

  • Assess and advise with regard to non-financial issues that may impact overall benefits, cost and risks of the Project

Selection

Original Proposal Teams

Long Beach CiviCore Alliance (LBCCA)

  • Lead Equity Member: Macquarie Capital Group

  • Equity Members: Lend Lease Investments and Mar Ventures/Continental

  • Contractor: Lend Lease

  • Lead Architect: Fentress

  • Landscape Architect: Civitas

  • Legal: Milbank

  • Underwriter: Bank of America Merrill Lynch

  • Facility Manager/ Operator: ABM Facility Services

Plenary Edgemoor Civic Partners (PECP)

  • Lead Equity Member: Plenary Group

  • Equity Member: Edgemoor Infrastructure & Real Estate (subsidiary of Clark Construction Group)

  • Contractor: Clark Construction Group

  • Lead Architect: SOM/ Kelly Sutherlin McLeoad

  • Landscape Architect: Gustafson, Guthrie Nichol

  • Legal: O’Melveny & Meyers LLP

  • Underwriter: Stifel

  • Facility Manager/ Operator: Johnson Controls

Proposal Evaluation & Scoring

See full Proposal Evaluation Document

Winner: Plenary Edgemoor Civic Partners

Agreed Contract Terms:

  • Design, build, finance, operate and maintain for 40 years post completion.

  • $520 million

See the finished project